The best possible solution

interview

The best possible solution

Basel Header

Renovations always bring many surprises and unforeseen situations. You must be very flexible and be able to react quickly to the circumstances. In the case of the Theater Basel, there were fundamental changes to the plan during the renovation, which had to be implemented as quickly as possible in order not to jeopardize the reopening.

Reading time: 3 min 36 sec

We interviewed the technical director and stage electrics manager on how they fared during the renovation:

Joachim Scholz, Technical Director, Theater Basel

My name is Joachim Scholz I have been the Technical Director at the Theater Basel for 15 years, managing the biggest multi-artistic theatre in Switzerland. Altogether the theatre consists of 3 stages in two different buildings. I believe this to be one of the best theatres at least on the European continent both artistically, as well as technically.

Our first project with Waagner-Biro Stage Systems was in 2008: the renewal of the lower stage machinery. We had an open tender with two finalists one of which could not guarantee the final completion on time. So the tender went to Waagner-Biro Stage Systems.

In 2010 we completed a new revolving stage wagon. 2012 the “Kleine Bühne” was renovated. In 2014 we renewed the drives in the “Schauspielhaus” and also the control system. And in 2015 we started renovating the upper stage machinery of the “Grosse Bühne” which we completed in 2016 and then replaced the rear stage hoists.

Stefan Möller, Chief Stage-Electrician, Theater Basel

Whatever a stage can have, the “Grosse Bühne” has it: lower stage machinery, upper stage machinery mobile proscenium,… Quite a number of axes…

The biggest part was the upper stage machinery the grid: All machines out everything old out.

Theater Basel 80 B9252 Sigrid Rauchdobler Large
Theater Basel 80 B2211 Sigrid Rauchdobler

Joachim Scholz

For a Technical Director it’s a bit like going through hell because you start…and meet difficulties then there are delays but operating the theatre comes first the next premiere has to happen and the curtain has to rise, and no-one should notice.

This is the biggest challenge.

Josef Ulzer, Project Manager, Waagner-Biro Stage Systems

In March or April, we received the order. The disassembly of the old machinery, however, started in June already. That meant we really only had a very small timeframe to complete the entire design for the mechanical and electrical design and to coordinate everything.

One benefit certainly was that the entire tender was awarded to Waagner-Biro Stage Systems. The control system the electrical system as well as the mechanics with an experienced project lead.

Joachim Scholz

My experience working with Waagner-Biro Stage Systems has always been very constructive. Together with Waagner-Biro Stage Systems and the consultants – and the city – we have always seen this as a shared project.

Whenever we had new requests Waagner-Biro Stage Systems fulfilled them. Whenever Waagner-Biro Stage Systems had any troubles delivering something on time we found solutions together.

I think that has always been special here. And that is why Waagner-Biro Stage Systems had fun working here. That is why this became a great stage.

The consultants and I had an idea and wrote it down in the tender. Then Waagner-Biro Stage Systems shared a different idea: We could do it this way. What do you think it?

And so during the process new ideas developed. So we adapted the order supplemented it and so the theater received the best possible solution. That had always been the goal: the best possible solution.

During the construction we decided to completely replace the mobile point hoists and to rebuild the entire grid.

Theater Basel 80 B9213 Sigrid Rauchdobler Large
Theater Basel 80 B9189 Copyright Sigrid Rauchdobler Large

Josef Ulzer

The roof trusses of the roof structure of this entire building are limited. So from the very first day we had been in contact with the local structural engineer.

Stefan Möller

The entire structure had to be calculated again. Does the building hold the weight of the new upper stage machinery? So that meant strengthening all the girders adding new iron girders the gridiron, on which we stand, is new as well.

So are all the structural mounts for the UNICORNs for the machines – all of that needed to be prepared. When I think of all the glitches and failures, we had in the past that has changed completely now.

Sure, in the beginning there had been some issues. Because during the commissioning you have to get accustomed to the new stage.

Joachim Scholz

Let’s not pretend I know of no stage that ran without errors upon commissioning. That stage does not exist. Only if you have another 6 months for commissioning it.

If you decide to renovate while running the theater, you have to plan for this. When something goes wrong you need a reliable partner who is here at once to see that things work.

Stefan Möller

They don’t let you down. Today I can say the stage operates without disruptions.

Josef Ulzer

There is really a lot of technology here a lot of possibilities for the stage crew to work here.

Joachim Scholz

Truly, every new season we did things on the stage that wouldn’t have been possible half a year earlier.

Stefan Möller

Looking at that this really is a Rolls Royce we have here.

Renovation of Theater Basel in Switzerland

Ines Schwabl image©Waagner-Biro Stage Systems

Ines Schwabl

Author

Angelika Albert-Knaus image©Waagner-Biro Stage Systems

Angelika Albert-Knaus

Author

7/16/2024

In this article

Waagner Biro Stage Systems

This might also be interesting for you