Anyone who thinks of Australia inevitably thinks of Sydney Opera House, which was designed by Danish architect Jørn Utzon. The opera house was inaugurated in 1973 by Queen Eliza-beth II.
With more than 10.9 million visitors every year, it is one of the most visited centres for performing arts, and Australia’s premier tourist attraction.
The opera house contains five performance venues with a total of 5,541 seats: the concert hall with 2,688 seats, the Joan Sutherland Theater (opera theater) with 1,547 seats, the drama theater with 544 seats, the playhouse with 398 seats and the Studio Theater with 364 seats.
Waagner-Biro Stage Systems has a long partnership with the Sydney Opera. In the 1970s, the company received the incredibly prestigious order, which at the time contributed to Waagner-Biro’s international breakthrough in the field of stage technology.
More than 40 years later, at the end of December 2015, Waagner-Biro Stage Systems won the international competition for the renewal of the entire stage technology of the Joan Sutherland Theatre. The output to be delivered by Waagner-Biro includes the complete renewal of the upper stage machinery with more than 100 hoists, new backstage lifts, and the refurbishment of the orchestra lifts. An extremely short closure time of approx. six months for this comprehensive renovation posed a major challenge.
This project also included Factory Acceptance Tests (FAT). The FATs for the winches already took place in August 2016, in December 2016 the FATs of the lower stage machinery followed, which were shipped in January 2017.
The winches were successfully approved from the customer’s at the Factory Acceptance Test.
For the FAT of the lower stage machinery we constructed two platforms, each 11.4 x 3.6 m with a 10.6 M hub, weighing approx. 18 tonnes. For the testing phase a generator was hired which would normally be used for live TV broadcasts like the Hahnenkammraces in Kitzbühel/Austria.
So we could also fry the odd egg as we were working.
The construction site at the opera house started work on May 25, 2017.
As early as April 2017, it was time for some of our employees to pack their bags and move to Sydney – even with their families. With a time window of barely six months for the conversion and a time difference of ten hours, it required the presence of the Project Manager, the Installation Manager and a member of the Mechanical Departement. This team was also involved in the planning and the FATs. The client has set a date of 14/11/2017 for “Theatre machinery project works complete”.
After seven months of refitting, it was time for New Year’s Eve: On December 31, 2017, the performance of the newly renovated Joan Sutherland Theater was raised with the performance “The Merry Widow”.
WB Stage: You will spend long periods of time in Australia. Why is that?
G. Seliger: Waagner-Biro Stage Systems is replacing the theatre machinery in the Joan Sutherland Theatre at the Sydney Opera House. I have been working on this project as design engineer since the very beginning in the tender phase and will continue to support the construction manager on site.
WB Stage: Was it clear from the beginning that you would need to spend a lot of time abroad for this project?
G. Seliger: It has been in discussion already in a very early phase of the project. For complex projects with a very short installation time like this one, it is definitely beneficial to have instant support from the design department on site, especially considering the time difference between Sydney and Vienna.
WB Stage: How did your wife react?
G. Seliger: My wife has been very supportive and open-minded regarding moving to Australia for the project. Fortunately, we have been able to organize for her to join me in Sydney for most of the time. Both of us looked forward to spending some time abroad.
WB Stage: What kinds of things do you need to think about when you settle in a new place?
G. Seliger: Apart from organisational matters, like getting a work visa and an apartment, I have to decide what to take with me for the next six months.
WB Stage: What particular challenges are you facing with this project?
G. Seliger: The major challenge is the very short time frame for the installation. Not only the theatre machinery will be replaced, but also other parts like HVAC, audio/video systems and fire protection systems. Accommodating the new equipment in a limited space was the next challenge.
WB Stage: You got involved during the offer phase? Why is that, and what were you able to contribute?
G. Seliger: To demonstrate Waagner-Biro Stage Systems qualifications and to show that we were the right partners for such a demanding job, we produced very extensive offer documents. I was responsible for making a design for the general arrangement of the upper stage equipment as well as load calculations and several other documents.
WB Stage: FATs (Factory Acceptance Test) were carried out. What was the reason for this?
G. Seliger: During last year we did two FATs for this project in Austria. One for the upper stage winches, while the other one included a complete setup of the new rear stage elevators, including equalisers and safety barriers. During these tests, the equipment was entirely assembled and commissioned in order to confirm their functionality and test all the required functions of winches and elevators.
WB Stage: What is the organisational process for FATs, what has to be done beforehand and how long does it take to carry out a FAT, or to organise it?
G. Seliger: Due to the size of the lower stage equipment, the first issue was to find a location where we could build up the entire system. After finishing the shop drawings and manufacturing the parts, the elevators were assembled, commissioned and tested internally over a period of approx. two months. Parallel to that, a testing program was developed and coordinated with our client and the theatre consultant of the project.
WB Stage: What are the advantages of FATs?
G. Seliger: The main advantage of a FAT is that you get the certainty that the equipment fits and works as it is supposed to do. We also had the chance to refine some of the mechanical, electrical and control-related aspects of the elevators. Furthermore we were able to test some of the special control modes, something that would usually not happen until the final commissioning on site. The FAT definitely facilitates the installation, which is very beneficial considering the very limited time we have on site.
WB Stage: When you conduct FATs, is the client also there on site?
G. Seliger: A few parties were present during the FAT, including the client, the theatre consultant, and the managing contractor of the renovation project.
The next project in the Opera House’s Renewal program is upgrading the world famous Concert Hall. This renewal includes the upgrading of the lower stage machinery, all the production rigging and the loud speaker and lighting hoists of the upper stage machinery. One of the biggest challenges will be to install modern machine hoists that can carry much higher loads, into the architecture of the building.
Waagner-Biro Stage Systems was also able to win this renovation in the international competition, thus extending the partnership with the Sydney Opera House.
The planning and preparation phase has already started. The house was closed in February 2020 to carry out the well-prepared renovation work. In 2022, the Sydney Opera concert hall is to be reopened with completely new technology.
The company also won a project in another major city in Australia – the State Theater at the Arts Center Melbourne.
Arts Centre Melbourne is not new to us either. The Arts Centre comprises of several venues and in 2013 Waagner-Biro Stage Systems delivered a modern C⋅A⋅T control system to them for the Hamer Hall, the complex’s concert hall.
The current project involves the renewal of over 100 decoration hoists in the theatre’s upper machinery. This includes dismantling the existing technology, installation of the new machines, and the complete renovation of the electrical and control systems. A deadline of just under 7 months is provided for all related renovation work.